Steel Structures

Steel Structures2026-10-28T16:29:00+00:00

Novelty Structures manufactures Steel Structures and Custom Steel Fabrications for Industrial and Construction Projects.

Welded Steel Structure Beams
Steel Fabrication Workshop

What is a Steel Structure ?

Structural steel frames are the ‘skeleton’ frame of a structure or a built asset, typically consisting of vertical columns and horizontal beams which are connected together in a grid.

Steel Beams are horizontal placed structural elements that carries loads applied laterally to their axis whereas steel columns are vertical aligned structural elements that transfer compressive loads.

Compared to other means of frames, steel frame structures offer numerous advantages, including their resilience to earthquakes, severe climatic conditions and design flexibility. Moreover, they have higher strength to weight ratio and strength to volume ratio, without compromising the durability.

Steel Welder at work

Why do we use Steel Structures ?

  • Structural Steel Frames are quick and easy to install and decommission, and offer fire resistance when properly treated.

  • Due to their offsite fabrication, they are much more cost effective compared to the timber or concrete frame structures.

  • Steel is often used in major projects to speed up development, reduce onsite risks, and minimise waste.

  • Steel profiles are available in a variety of dimensions, grades and can be bespoke fabricated. Flexible fabrication allows versatile structure design for the designers.

  • Steel is durable and it requires less maintenance, hence reducing the costs throughout the structure’s lifetime.

  • Due to its offsite construction, steel offers advanced material quality traceability compared to the other means of frames.

Steel Structure Fabrication Operations

Material Procurement

  • Sourcing: Steel plates, beams, bars, and other required components are procured based on specifications.

  • Traceability: The certificates and heat numbers of the raw materials are recorded during the fabrication journey

Stainless Steel Fabrication

Cutting & Bending

  • Cutting: Steel components are cut to desired sizes using equipment such as:

    • Laser cutting | Plasma cutting |Oxy-fuel cutter |Water jet cutting
  • Bending: Steel is bent, rolled, or shaped into specific forms using:

    • Press brakes | Rollers

Welding & Assembly

  • Welding: Steel components are welded using various welding techniques (MIG, TIG, arc welding, etc.).

  • Assembly: Smaller steel components are pre-assembled into larger modules to facilitate installation.

Quality Control

  • Dimensional Accuracy: Components are checked to ensure precise dimensions and alignment.

  • Weld Quality: Welds are tested for defects with NDT; Visual testing, Dye Penetrant Testing, Magnetic Particle and X-Ray Testing

Surface Treatment

  • Cleaning: Removal of impurities, rust, and scale using sandblasting or chemical cleaning.

  • Coating: Application of protective coatings such as:

    • Galvanization | Primer paints | Epoxy or powder coatings
steel welding work

Packaging & Shipment

  • Packaging: Fabricated steel components are carefully packed to avoid damage.

  • Loading and Transporting: Transported to the construction site using trucks, cranes, or shipping containers.

Steel  Types

Steel structure fabrication involves a variety of materials to ensure strength, durability, and suitability for specific applications. Below are the primary materials used:

  • Carbon Steel:
    • Most commonly used steel.
    • High strength and durability.
  • Alloy Steel:
    • Steel mixed with other elements like chromium, nickel, or molybdenum for enhanced properties.
    • Used in high-stress environments
  • Stainless Steel:
    • Contains chromium for corrosion resistance.
    • Often used in architectural projects and environments with exposure to moisture or chemicals.
  • Galvanized Steel:
    • Coated with zinc for rust and corrosion resistance.
    • Used in outdoor or marine environments.

Steel Structure Components

1. Structural Components

  • Plates: Flat steel sheets used for base plates, gussets, and floor decking.
  • Beams: I-beams, H-beams, or wide flange beams used as primary load-bearing members.
  • Angles: L-shaped steel pieces used for bracing and framing.
  • Channels: U-shaped steel sections for support in various applications.
  • Pipes and Tubes: Round, square, or rectangular sections for columns, braces, and trusses.
  • Bars and Rods: Solid steel sections used in reinforcements and smaller structural elements.
Steel Beam and Column

2. Fasteners and Joining Materials

  • Bolts: High-strength bolts for secure connections.
  • Anchors & Inserts: For securing steel structures to reinforced concrete
  • Nuts and Washers: Used alongside bolts for fastening.
  • Welding Materials: Wires for MIG/TIG welding.

3. Coatings and Protective Materials

  • Hot Dip Galvanization: Hot Dipped Zinc coating for corrosion resistance.
  • Paints: Epoxy, polyurethane, or acrylic paints for aesthetic and protective purposes.

4. Additional Materials

  • Gratings: Steel mesh or grids used for flooring and walkways.
  • Steel Cables: Used in tension systems and suspension designs such as bridges.
  • Steel Reinforcement (Rebar): Used for reinforcing concrete structures in composite construction.

Quality Control

1. Material Quality Control

  • Material Certification: Verifying that raw materials (steel plates, sections, bolts, and weld consumables) meet specified grades and standards (e.g., ASTM, EN, or ISO).

  • Traceability: Maintaining records of materials to ensure their source and batch comply with project specifications.

2. Dimensional and Tolerance Control

  • Inspection of Fabrication Drawings: Ensuring shop drawings align with design requirements.

  • Alignment and Dimensional Checks: Verifying dimensions and tolerances of cut plates, rolled sections, and assembled parts using measuring tools.

Heat Exchanger Quality Inspection
  • Welding Procedure Qualification (WPS/PQR): Ensuring welding is performed according to qualified procedures.

  • Welder Qualification: Certifying that welders meet standards such as AWS D1.1 or EN 1090.

  • Non-Destructive Testing (NDT):

    • Visual Inspection (VT): Checking for surface defects like cracks, porosity, or undercuts.
    • Ultrasonic Testing (UT): Identifying subsurface defects in welds.
    • Radiographic Testing (RT): Using X-rays or gamma rays to inspect internal weld quality.
    • Magnetic Particle Testing (MT) and Dye Penetrant Testing (PT): Detecting surface or near-surface defects.
Painting Quality Check

4. Surface Treatment

  • Surface Cleaning: Preparing the steel surface free of contaminants like rust, oil, or mill scale before painting or coating (typically assessed using SSPC or ISO cleanliness standards).

  • Coating Thickness: Measuring the thickness of protective coatings using dry film thickness (DFT) gauges.

5. Assembly and Fit-Up

  • Fit-Up Checks: Ensuring proper alignment and fit of bolted or welded joints before assembly.

  • Trial Assembly: Pre-assembling critical structures to verify fit-up before delivery to the site.
  • Bolt Tightening: Verifying bolt torque using torque wrenches or tensioning equipment for connections.

Selecting the Right Coating for Steel Structures

The coating of a steel structure serves both protective and visual purposes. It helps protect the steel against corrosion while providing the colour, gloss and surface appearance required for the project. Selecting a suitable system therefore involves considering the operating environment, expected durability, maintenance requirements and architectural finish together.

Environmental Exposure and Corrosion Categories

Painted steel beam-to-column connection showing the surface finish.

Coated steel connection

Moisture, condensation, airborne salts and industrial pollutants influence the corrosion of steel. ISO 12944-2 classifies atmospheric environments into corrosivity categories, providing a basis for selecting protective paint systems.

Corrosivity category Typical environments
C1 — Very low Heated buildings with clean atmospheres, such as offices, shops and schools.
C2 — Low Rural areas with low pollution and unheated buildings where condensation may occur, such as storage facilities.
C3 — Medium Urban and industrial atmospheres with moderate pollution, coastal areas with low salinity, and humid production rooms with some air pollution.
C4 — High Industrial areas and coastal locations with moderate salinity, together with environments such as chemical plants and swimming pools.
C5 — Very high Industrial environments with high humidity and aggressive atmospheres, coastal areas with high salinity, and interiors with almost permanent condensation and substantial pollution.
CX — Extreme Offshore environments with high salinity and industrial environments with extreme humidity and aggressive atmospheric conditions.

These examples provide guidance rather than a definitive classification for every location.

The assessment should reflect the conditions around the steelwork itself. Indoor structures may experience significant condensation or industrial contamination, while different parts of the same structure may have different exposure conditions. Sheltered connections, moisture-retaining areas and surfaces exposed to salt deposits require consideration alongside the general site environment. Steelwork immersed in water or buried in soil is assessed separately.

Appearance and Architectural Requirements

For exposed steelwork, the coating also contributes to the finished appearance of the building or installation. Colour, gloss and surface texture should suit the architectural design and the visibility of the steel components. Maintaining the desired appearance over time is a separate consideration from maintaining corrosion protection; coating selection should address both aesthetic and anti-corrosive durability.

The appearance of painted steel also depends on the underlying fabrication. Weld profiles, surface irregularities and visible connections influence the finished result.

Coated steel frame near a coastal environment.

Coastal steelwork

Where appearance is important, the required surface finish should be agreed before fabrication, with representative samples used where appropriate to establish expectations.

Durability and Maintenance

Coating durability describes the expected period before first major maintenance. Selection should consider how easily the steelwork can be inspected, cleaned and recoated during service. Structures that are difficult to access may require a different maintenance strategy from readily accessible components.

Defining the Complete Coating System

A corrosivity category or colour reference alone does not provide a complete coating specification. The selected system should define the substrate preparation, compatible coating products, number of coats, nominal dry film thickness and application conditions. Chemical exposure, operating temperature and abrasion may introduce additional requirements.

Surface preparation and application quality are essential to achieving the intended performance. The specification should also address inaccessible surfaces, site connections and repairs following transport or assembly, so that the completed structure receives consistent protection and the agreed visual finish.

Practical Case Studies

A steel structure can fully satisfy design calculations and yet present major challenges during procurement, fabrication, surface protection, or site assembly. Most field issues occur at key operational interfaces: specified steel sections are unavailable, connection bolts cannot be reached during erection, or finished assemblies exceed transport limits. Resolving critical engineering decisions early gives project owners, fabricators, and site teams actionable control over quality, schedule, and cost. Below are detailed real-life project case studies illustrating how proactive planning overcomes these challenges.

Steel beam welded to an extended end plate bolted to a column flange.

Steel connection access

Steel frame in an urban construction setting.

Urban steel frame

Case Study 1: Zero-Rework Steel Assembly Through Pre-Erection Site Verification

A multi-story commercial structure featuring tight site boundaries and complex structural framing was planned in a dense urban centre. While 3D CAD models confirmed that all structural members fitted perfectly in the completed configuration, field conditions presented major risks. Urban sites often lack storage space, crane lifting radii are severely constrained, and tight connection nodes can prevent installers from inserting bolts, positioning tightening tools, or performing mandatory weld inspections.

Engineering Solution & Implementation:

To ensure flawless execution on site, Novelty Structures conducted a comprehensive pre-erection assembly review covering five essential operational pillars before releasing structural steel for manufacturing. The erection sequence was developed in coordination with the frame designers and structural engineers to ensure structural stability at every intermediate construction stage.

Steps of Pre-Fabrication Assembly Review:

Steps  Focus Areas
1. Site Access Confirm delivery truck turnarounds, staging area dimensions, and component movement pathways from unloading points to final installation positions.
2. Lifting Capacity Verify component assembly weights against real crane capacity charts at actual operating radii, not just headline crane capacities.
3. Working Space Ensure installer clearance for inserting bolts, positioning hydraulic torque wrenches, reaching weld seams, and conducting quality inspections.
4. Erection Sequence Evaluate member installation sequence to guarantee that erecting one structural element does not block access to subsequent connection nodes or secondary trades.
5. Temporary Stability Design temporary guy lines, bracing systems, and intermediate supports required to maintain frame stability before permanent bracing is fully secured.

Results:

During the review, the team identified three primary beam-to-column connection nodes where field bolt insertion would have been physically impossible due to adjacent architectural column covers. By catching these clearance issues prior to cutting steel, the connection details were modified to side-plate splices with formal structural engineering approval. This proactive check eliminated expensive site re-engineering, field torching, renewed non-destructive testing (NDT), and paint repairs during erection, keeping the project strictly on schedule.

Assembly Efficiency Principle:

Checking tool clearance, lifting radii, and temporary frame stability before cutting steel preserves cost-effective design options that become extremely expensive to recover once members arrive on site.

Case Study 2: Containerised Modular Trusses for Heavy Structures

A major logistics terminal project required massive roof trusses to span wide, unobstructed operational bays. However, the site was located in a densely populated industrial zone accessible only via narrow roads, underpasses, and strict transport width restrictions. Standard oversized heavy-haulage transport was logistically impossible, and fully welding the trusses on site was ruled out due to tight space constraints, poor weather protection, and high labour overheads.

Solution & Implementation:

To bypass these severe logistical bottlenecks, Novelty Structures developed a modular truss design that completely separated transport dimensions from final operational dimensions.

Steel truss components packed inside a shipping container.

Containerised truss components

Instead of attempting to ship bulky, pre-welded assemblies, the structural trusses were engineered into containerised sub-assemblies. Each main truss was split into 15 precision-fabricated components specifically dimensioned to fit inside standard shipping containers.

Comparison of Delivery Types

Assembly Type Advantages Constraints
Large Factory Assemblies Maximizes controlled workshop welding and coating; minimizes site labor. Requires special transport permits, wide clearance routes, and heavy site cranes.
Containerized Sub-Assemblies Highly flexible shipping in standard containers; lower freight cost; protection from transit damage. Requires engineered site joints, clear component tagging, and detailed assembly instructions.
Ground Pre-Assembly Node Forms massive structural spans safely at ground level away from main site traffic. Demands dedicated staging space, temporary ground supports, and planned tandem lifting.

The sub-assemblies were shipped safely via standard container freight. Upon arrival, a ground-level pre-assembly area was established adjacent to the installation zone, clear of terminal traffic. Workers assembled the 15 components into full-span structural trusses on temporary ground jigs, completed torque checks and field NDT, and then lifted the completed spans directly into place using a single heavy crane lift. This approach eliminated transit bottlenecks while maintaining workshop-grade connection precision.

Truss components packed for container transport.

Container transport

Truss components being assembled on ground-level supports.

Ground truss assembly

Crane lifting an assembled steel truss into position.

Truss installation

Key Takeaway:

Shipping units and lifting units do not need to be identical. Designing structural components for containerised transport and assembling them near the installation area drastically reduces freight costs and eliminates route bottlenecks.

Case Study 3: Material Substitution

Project Context & Challenge:

During a time-critical warehouse facility build for a regional client, severe global steel market disruptions occurred. The original structural design specified custom long-span steel joists. Upon placing mill orders, the project team learned that the steel joists faced lead-time delays of 12 to 16 weeks due to mill rolling schedules and raw material shortages—a delay that threatened the entire project completion date.

Engineering Solution & Implementation:

Recognising that delaying construction by several months was unacceptable, Novelty Structures initiated an early material availability review to evaluate structural alternatives while design choices remained open. Instead of waiting for specialised mill production schedules, the procurement and engineering teams reviewed readily available stock items across regional steel distributors.

Universal beam, channel and cold-formed purlin sections.

Structural steel sections

Structural steel roof framing and purlins.

Roof framing

We redesigned the roof framing system using a combination of widely stocked beams, channels, and cold-formed purlins to replace the long-lead open-web steel joists. We checked substitution criteria beyond basic strength, ensuring member depth, cross-sectional geometry, connection stiffness, web buckling resistance and deflection limits satisfied all structural code requirements.

We obtained immediate structural engineer sign-off and updated fabrication drawings before purchasing materials, ensuring zero waste or non-compliant stock acquisition.

Key Verification Checklist for Structural Steel Substitution

Substitution Factor  Verification 
Section Availability Verify stock status, exact mill rolling dates, and lead times against the master project schedule.
Steel Grade & Subgrade Ensure toughness (impact energy), yield strength, and delivery condition (e.g., JR, J2, K2) match spec requirements.
Member Geometry Check overall section height and flange width to prevent architectural envelope or ceiling clearance conflicts.
Connection Compatibility Re-calculate bolt shear/tension and weld strength for modified flange/web thicknesses.
Cutting Waste & Logistics Evaluate ordered stock lengths against nesting schedules to minimize scrap percentages.

By adopting readily available structural sections, the delivery window was shortened by nearly 10 weeks (over two months). Fabrication started immediately, allowing the owner to enclose the building ahead of winter and avoid substantial liquidated damages.

Procurement Strategy Insight:

Catalogue availability does not equal confirmed delivery. Engaging procurement early and establishing pre-approved section substitution pathways prevents mill rolling delays from derailing project schedules.

Case Study 4: BIM & CNC Integration

A warehouse project for an international client featured large-span roof trusses and complex internal mechanical, electrical, and plumbing (MEP) infrastructure. With multiple design teams working simultaneously, spatial collisions between structural framing, heavy cranes, and HVAC ducting posed high risks of costly field rework and site delay.

Engineering Solution & Implementation:

To address these risks, Novelty Structures implemented a fully integrated Building Information Modeling (BIM) workflow that connected design models directly to automated fabrication machinery. Weekly multi-trade 3D model federations were conducted 2 to 3 months prior to shop fabrication. This integrated approach allowed the detailing team to generate high-precision structural models, shop/erection drawings, bill-of-materials (BOM) data, and numerical control (NC/CNC) files directly from the coordinated 3D environment.

How Integrated BIM & Automated Manufacturing Protect Project Performance

Conceptual model showing structural steel coordinated with building services.

Coordinated structural model

CNC machine drilling a structural steel beam.

CNC beam drilling

Project Performance Dimension Direct Benefits of Integrated BIM & Workshop Automation
Quality Control Eliminates repetitive manual data entry. Connection clashes and tool access limitations are resolved months before steel is cut.
On-Time Delivery Directly connects approved BIM geometry with material requirements and automated CNC drilling/sawing equipment.
Scheduling Visibility Provides real-time tracking of shop fabrication, surface coating, and transport dispatch against erection sequences.
Budget Control Enables rapid evaluation of proposed design revisions, instantly identifying affected members and eliminating unexpected field rework.

A crucial takeaway from this project is that a coordinated model only prevents errors if the shop floor operates strictly on approved, up-to-date data. A formal digital release protocol was instituted: prior to issuing production files to CNC sawing and drilling machines, shop management cross-verified that the 3D model, detail drawings, material lists, and CNC instructions described the exact same approved revision, while automatically revoking superseded files.

BIM Governance Principle:

Digital model coordination is only as effective as revision control. Confirming that 3D models, shop drawings, BOMs, and CNC machine files share the exact same approved revision before production release prevents costly shop floor rework.

How can we help you ?

Novelty Steel is an experienced fabricator of steel structures for many industries including construction, mining, energy, machinery.

With vast CNC Machinery Park and experienced engineering team, Novelty Steel produces bespoke steel frames according to the EN 1090-2 European Norms.

Some examples of the fabrications are:

Contact our team to further discuss your needs.

FAQ

What industries benefit from steel structure fabrication?2024-12-23T23:17:15+00:00

Steel structure fabrication serves a wide range of industries, including:

  • Construction (commercial and residential buildings, warehouses, etc.)
  • Industrial (factories, refineries, and power plants)
  • Transportation (bridges, rail infrastructure, etc.)
  • Energy (oil and gas platforms, wind turbine structures)
  • Agriculture (barns, silos, and equipment sheds)
What types of steel structures do you fabricate?2024-12-23T23:17:52+00:00

Our services cover the fabrication of:

  • Building frameworks
  • Beams, columns, and trusses
  • Stairs, handrails, and ladders
  • Custom platforms and walkways
  • Storage tanks and silos
  • Bridges and structural components
How long does it take to fabricate a steel structure?2024-12-23T23:18:28+00:00

The timeline for steel structure fabrication depends on factors such as project size, complexity, and customization requirements. Smaller projects may take a few weeks, while larger or more intricate projects could take several months.

What is your geographic service area?2024-12-23T23:19:13+00:00

We provide steel fabrication services locally, regionally, and internationally, depending on the project’s scope and logistics. Contact us to discuss your location.

How much does steel structure fabrication cost?2024-12-23T23:19:49+00:00

The cost varies based on factors such as material type, project size, design complexity, and additional services (e.g., installation). Contact us for a detailed quote.

Can you handle large-scale projects?2024-12-23T23:20:30+00:00

Yes, our facilities and team are equipped to handle projects of any size, from small-scale custom components to large industrial or commercial structures.

What kind of steel finishing do you provide?2024-12-23T23:21:24+00:00

Yes, we offer a variety of steel finishing services to enhance durability, aesthetics, and resistance to corrosion. These include:

  • Powder coating
  • Galvanizing
  • Painting
  • Sandblasting and surface treatment
What welding techniques do you use?2024-12-23T23:22:04+00:00

Our team uses a range of welding techniques to suit different fabrication requirements, including:

  • MIG (Metal Inert Gas) welding
  • TIG (Tungsten Inert Gas) welding
  • Arc welding
  • Spot welding
    Each method is chosen based on the project’s material, thickness, and strength requirements.
How do you ensure the precision of fabricated components?2024-12-23T23:22:39+00:00

We use advanced technologies like CNC (Computer Numerical Control) machines, laser cutting, and 3D modeling software to ensure precision and accuracy in every fabricated component.

How do you handle transportation of fabricated steel components?2024-12-23T23:23:14+00:00

We provide logistics support, including safe packaging, transport, and delivery of fabricated steel components to your project site. We coordinate with reliable shipping providers to ensure timely and secure delivery.

Can you fabricate steel structures for seismic or high-wind zones?2024-12-23T23:24:10+00:00

Yes, we have extensive experience in fabricating steel structures that are designed to withstand earthquakes, high winds, and other extreme conditions.

How do you manage large-scale fabrication projects?2024-12-23T23:24:53+00:00

For large-scale projects, we follow a streamlined process that includes:

  • Detailed project planning and scheduling
  • Dedicated project managers
  • Efficient material procurement
  • Regular progress updates for clients
Can you fabricate modular steel structures?2024-12-23T23:25:26+00:00

Yes, we specialize in modular steel structures that are pre-engineered and fabricated for quick on-site assembly. These are ideal for temporary or permanent installations like prefabricated buildings, shelters, or portable offices.

How do you accommodate changes during the fabrication process?2024-12-23T23:25:57+00:00

We understand that project requirements may evolve. Our team maintains clear communication and flexibility to accommodate changes, ensuring minimal disruption to timelines and budgets.

Welding works for metal fabrication

Completed Projects

Products

Steel Structures

Plant Engineering Fabrications

Bulk Material Handling Structures 

Steel Buildings

Steel Silos

Hoppers & Chutes

Steel Trusses

Mezzanines & Stairs

Steel Tanks

Services

Laser Cutting 

Metal Bending

Plate Rolling

Machining

Welding

Painting

Go to Top